Site Cuts

Greenbank Dream Home — Multi-Pad Site Cut

Greenbank, Logan Multi-day build View Site Cuts
Wide view of the Greenbank site cut showing benched earth levels and an excavator beside the cut

Project Scope

Full site cut and pad preparation for a new acreage build — a seven-bedroom, five-bathroom home, a separate guest house and a large shed, each set out on its own level.

The Challenge

A large, sloping bush block that needed three separate building platforms — house, guest house and shed — each set out to its own level and tied together. All up it meant moving over 700m³ of soil in a balanced cut and fill, with the fill placed and compacted to a standard the geotechnical engineer would sign off before any slab work.

How We Approached It

  1. 1
    Set out the levels and building footprint for the home, guest house and shed on day one
  2. 2
    Bulk site cut with the excavators, cutting the high side down toward the set-out levels
  3. 3
    Balanced cut and fill — over 700m³ of soil moved to form the three pad levels
  4. 4
    Fill built up in thin ~100mm layers, each one compacted with the roller before the next went on
  5. 5
    Sandstone retaining installed to hold the level changes between the pads
  6. 6
    Geotechnical compaction testing to confirm the pads before handover
Equipment Used
  • 8.5T excavator
  • 1.7T excavator for trim work
  • Compaction roller
  • Laser level for set-out
Materials Handled

Over 700m³ of soil cut and re-used as compacted fill across the three pad levels — a balanced cut and fill kept on site.

Outcome

Three pads cut and built to level and compacted to around six times the minimum spec — signed off by the geotech and ready for the builder to move into footings and slab.

On Site

Prepared earth pad at Greenbank with a tripod in the foreground and an excavator beside the tree line
A broad view across the prepared pad, with levelling equipment on site.
Kobelco excavator bucket above the exposed earth and cut face on the Greenbank site
Excavation across the Greenbank block, showing the cut face and working area.

Key Takeaways

  • On a multi-building block, setting all the pads out together keeps everything tying in and the builder moving
  • Balancing cut and fill on site avoided carting hundreds of cubic metres of soil away
  • Compacting fill in thin layers and testing it is what lets the geotech sign the pads off with confidence