Project Scope

Steep hinterland block — 1.8m cut with retaining wall bench prep. Boulder breaking required for the lower bench.

The Challenge

1.8m cut into a steep slope required engineer-designed batter and retaining wall combination. Lower bench area had buried boulders — couldn't be quoted from the street.

How We Approached It

  1. 1
    Site visit with the engineer to walk the design
  2. 2
    Topsoil stripped and stockpiled for the terrace gardens
  3. 3
    Bulk cut in three benches following the engineer's design
  4. 4
    Boulder pocket hit on lower bench — hydraulic breaker fitted to handle
  5. 5
    Bench leveled and trimmed to retaining wall trade's requirement
  6. 6
    Cut spoil pushed and shaped into the lower terrace
Equipment Used
  • 5T excavator with rock breaker
  • 3T excavator for bench trim
  • Plate compactor
Materials Handled

Zero cart-away — all spoil reused on lower terrace and garden shaping

Outcome

Bench delivered ready for retaining wall trade. Spoil reused on the lower garden terrace.

Key Takeaways

  • On steep blocks, planning the spoil destination upfront saves real money
  • Coordinating with the engineer at site visit catches design issues early
  • Hidden boulders are a Currumbin Valley reality — quote with rock allowance