Ashmore Horse Arena Construction

Project Scope
60m × 30m horse arena pad — strip, level, base layer, drainage, and surfacing prep.
The Challenge
Large flat pad in a property that drained naturally to one corner. Arena needed positive drainage in two directions plus a perforated drain spine to keep the surface dry through wet seasons.
How We Approached It
- 1Topsoil stripped from full 1,800m² area
- 2Bulk cut to subgrade with crown for drainage fall
- 3Geofabric laid over compacted subgrade
- 4Perforated agi-line drain spine installed with surrounding 20-40mm RCA
- 5Compacted road base layer 100mm deep
- 6Final trim to surface-contractor's tolerance
Equipment Used
- 5T excavator
- Bulldozer for shaping
- Roller compactor
- Laser level
Materials Handled
210m³ topsoil stockpiled for paddock topdressing
Outcome
Arena pad to design spec, ready for the surface contractor. Owner riding within the month.
Key Takeaways
- Drainage planning at the start saves a wet, unrideable arena later
- Stockpiling topsoil for paddock use was a real value-add for the owner
- Roller compaction in lifts gives the surface a stable, long-lasting base